Construction Set To Begin On Bellflower Monday
During construction the westbound traffic will be maintained; however, eastbound traffic will be closed from Georgetown Drive to Center Street.
Chagrin Valley Paving will begin construction on Bellflower Road this Monday
Work will include the repair and resurfacing of Bellflower Road from Route 306 to Center Street.
During construction the westbound traffic will be maintained; however, eastbound traffic will be closed from Georgetown Drive to Center Street.
A detour, using Route 2, will be established to redirect the eastbound traffic. Access to all properties will be provided but traffic delays should be expected throughout the project.
The work will be performed between the hours of 7 a.m. and 9 p.m., Monday through Friday and should be completed by August 25.
Contact the Engineering & Building Department at building@cityofmentor.com or (440) 974-5785 with any questions.
Kathie
8:39 am on Tuesday, June 19, 2012
The city was contacted by the contractor late Monday, June 18 -- the project will not get underway until NEXT Monday, June 25.
Jason Lea
8:48 am on Tuesday, June 19, 2012
Ah, noted.